Chapter 1 of 62Space & aerospace4 min read · 2 exhibits

Executive Summary and Reading Guide

Which parts cap how fast the space economy can grow, who makes them, and what should decision-makers take from this study?

Chapter summary

satellites themselves are no longer the scarce item.

Key takeaways

  1. 1

    SpaceX builds about 70 Starlink satellites a week and Amazon says it builds about 30 a week; in 2025 the world launched 4,492 payloads, ten times the 2019 figure.

  2. 2

    What is scarce is a short list of parts that only a handful of qualified suppliers make, that take a year or more to deliver, and that cannot be swapped without requalification.

  3. 3

    Setcoin's bottleneck scorecard ranks five at the top: optical inter-satellite terminals bought on the open market, solid rocket motors, launch slots, radiation-hardened processors and III-V multi-junction solar cells.

At a glance

Exhibit 1.1

Satellites are plentiful; a short list of parts is not

4,492

payloads launched in 2025, ten times 2019

~70 a week

SpaceX satellite production rate

20 of >500

SDA Tranche 1 optical terminals delivered by Jan 2025

99%

China's share of primary gallium

Source: Setcoin space engine (SATCAT), 18 Oct 2026; SpaceX filing; GAO; USGS; Space Supply Chain Bottlenecks: Components, Minerals and Capacity, 2026–2030, Setcoin Research (October 2026)

The chapter · 982 words · 2 exhibits

Which parts cap how fast the space economy can grow, who makes them, and what should decision-makers take from this study?

The short answer. satellites themselves are no longer the scarce item. SpaceX builds about 70 Starlink satellites a week and Amazon says it builds about 30 a week; in 2025 the world launched 4,492 payloads, ten times the 2019 figure. What is scarce is a short list of parts that only a handful of qualified suppliers make, that take a year or more to deliver, and that cannot be swapped without requalification. Setcoin's bottleneck scorecard ranks five at the top: optical inter-satellite terminals bought on the open market, solid rocket motors, launch slots, radiation-hardened processors and III-V multi-junction solar cells. Beneath the solar cells and radio parts sit two minerals, gallium and germanium, of which China produces 99% and most respectively; its ban on exports to the United States is suspended only until 27 November 2026. The largest constellation builders have escaped many of these limits by making parts themselves, which moves the bottleneck onto everyone else: defence programmes, European sovereign systems and smaller operators.

Ten findings

#FindingChapter
1Satellite output has grown tenfold since 2019, almost all of it inside two vertically integrated companiesChapter 3, Chapter 8
2The binding constraints are specific parts with few qualified suppliers, not satellites or factories in generalChapter 44
3Merchant optical terminals rank first: the US defence constellation needed more than 500 and had 20 by January 2025Chapter 14
4Solid rocket motors are shared with missiles, and missile demand is winning the capacityChapter 19
5III-V solar cells are made in megawatts a year; mega-constellations need tens of megawatts, so they use siliconChapter 11, Chapter 12
6Germanium prices roughly doubled in 2025; the cell cost effect is real but small, the availability effect is largeChapter 13, Chapter 48
7Small parts, switchgear and connectors, now have the longest lead times, up to 27 monthsChapter 22
8Workforce and test capacity are slower to fix than factoriesChapter 28, Chapter 31
9Vertical integration and acquisitions (Rocket Lab bought Mynaric and agreed to buy Iridium) are reshaping the merchant baseChapter 51
10Closing the gaps to 2030 needs roughly $2–5 billion of targeted capacity, not tens of billionsChapter 49

Key numbers

MeasureValueSource
Payloads launched worldwide, 20254,492 (453 in 2019)Setcoin SATCAT analysis, 18 Oct 2026
Share of 2025 payloads that were Starlink71%Setcoin SATCAT analysis
SpaceX satellite production rate~70 a weekSpaceX registration statement, 2026
Optical terminals for SDA Tranche 1 Transport>500 needed; 20 delivered by Jan 2025GAO, Feb 2025
Germanium metal price$1,991/kg (2024) → $4,100/kg (2025 average)USGS, 2026
China's share of primary gallium99%USGS, 2026
Longest reported lead timeSpace-grade switchgear, up to 27 monthsPwC/AIA study, March 2026 (as reported)
Credentialed assembly workers a year vs hires~13,000 vs ~244,000RAND, Aug 2026 (as reported)

The bottleneck scorecard in one table

Source table: Score (0–100) (10 rows, shown as an exhibit above)
RankComponentScore (0–100)Tier
1Optical inter-satellite terminals (merchant)83Critical
2Solid rocket motors81Critical
3Launch slots77Critical
4Radiation-hardened processors and FPGAs75Critical
5III-V multi-junction solar cells75Critical
6Space-grade power switchgear71Serious
7Infrared focal plane arrays70Serious
8Connectors and harnesses68Serious
9GaN and GaAs RF parts67Serious
10Actuators and nozzles64Serious

Setcoin scorecard. lead time, supplier concentration, demand growth, difficulty of substitution and geographic exposure, each scored 1–5 and weighted 25/25/20/15/15. Method in Chapter 4; full ranking in Chapter 44.

Exhibit 1.2

Five parts score as critical; optical terminals rank first

The ten highest bottleneck scores (Setcoin scorecard) · score, 0–100

Optical inter-satellite terminals83
Solid rocket motors81
Launch slots77
Rad-hard processors and FPGAs75
III-V solar cells75
Space-grade switchgear71
Infrared focal planes70
Connectors and harnesses68
GaN and GaAs RF parts67
Actuators and nozzles64
Source: Setcoin scorecard, October 2026; Space Supply Chain Bottlenecks: Components, Minerals and Capacity, 2026–2030, Setcoin Research (October 2026)

The five interactive models

ModelQuestion it answers
Bottleneck scoreWhich parts rank as chokepoints when you change the weights? (Chapter 44)
Constellation bill of materialsDoes component supply cover the satellites planned for a year? (Chapter 46)
Lead-time schedule riskWhen must each part be ordered, and which one sets the launch date? (Chapter 47)
Mineral shockWhat does a germanium price spike do to solar cell cost? (Chapter 48)
Electric propulsion propellantHow much xenon, krypton or argon does a constellation need, and at what cost? (Chapter 17)

Each model can be downloaded as a spreadsheet with live formulas.

How the study is organised

PartChaptersContent
I. FoundationsChapter 2 to Chapter 8The bill of materials, demand from the satellite catalogue, the scoring method, supply tiers, vertical integration
II. ComponentsChapter 9 to Chapter 25One chapter per critical part: electronics, solar, minerals, optical terminals, propulsion and propellants, motors, attitude control, power, small parts, RF, structures, sensors
III. CapacityChapter 27 to Chapter 32Satellite factories, test facilities, launch, workforce, qualification
IV. Policy and geographyChapter 33 to Chapter 40Export control, critical minerals, tariffs, single points of failure, the US, Europe, China, other nations
V. Demand casesChapter 41 to Chapter 43Defence, mega-constellations, direct-to-device
VI. Synthesis and toolsChapter 44 to Chapter 59Scorecard, bill-of-materials balance, lead-time risk, mineral shock, capacity build, consolidation, vendor map, checklist, risks, signals, method

Appendices. A, component reference table; B, glossary; C, Setcoin's satellite-catalogue dataset.

Reading paths

ReaderSuggested path
Satellite programme managerChapters 2, 4, 14, 22, 28, 47, 54
Component supplierChapters 6, 8, 44, 46, 49, 51, 53
Government and defence buyerChapters 19, 33, 34, 37, 38, 41, 49
Capital providerChapters 1, 8, 44, 49, 51, 56, 57
NewcomerChapters 2, 3, 6, 27, 61

How this study relates to the series

This is the seventh study in Setcoin's space research programme. Study S5 (launch economics) explains the launch capacity that this study treats as one bottleneck among several; Study S4 (defence space and Golden Dome) sets out the defence demand that competes for the same parts; Study S6 (direct-to-device) covers the large-array satellites that push RF and power supply hardest. Facts are as of October 2026; Setcoin calculations and illustrations are labelled.

Check the live record Space Contracts & Tender Radar · Constellation Deployment Monitor · Space Claim Check (free)

Ask about this chapter

Answers drawn from every Setcoin report and the live Atlas. Each statement links to the passage behind it.

Summarise "Executive Summary and Reading Guide" in five pointsWhich figures in this chapter matter most to an investment committee?What should I check on the Atlas after reading this?
Subscription

Ask is included with every subscription

Cited answers across every report and the Atlas, with follow-up questions and a hand-off to the opportunity finder.

Research for professional investors. Not investment advice, and not an offer of any security or fund interest.