Setcoin Equipment Map

What the world’s pipeline will buy — and where supply will run short.

Every pre-FID project on the Atlas, translated into the equipment it will tender: by category, region and lead time, set against what suppliers can actually deliver.

$3.00tnmodeled equipment demand, pre-FID pipeline
15,423projects with a capex figure
$632.5bnin categories with critical lead times
8,670projects consented, EPC not yet awarded
Ask the map

What will the pipeline buy in your category?

Pick what you sell and where. Everything below is computed from the live Atlas — 15,421 pre-construction projects with a capex figure — through the same equipment model the paid product uses.

—modeled demand for your category
—projects that will buy it
—of these projects have a permit or grid consent on record
—lead time · supply risk

When the orders come

By project stage: awarded projects are buying now; tendering ones within about a year; pre-tender ones in one to three years (stage-based estimate).

    Who buys it

    Modeled demand for your category by the sector of the project.

    Where it is

    Top countries and US states by modeled demand in your selection.

    Can you deliver in time?

    Move the slider to your next free production slot. Delivery = slot + your lead time; projects need delivery roughly 18 months out when awarded, 30 when tendering and 48 when pre-tender (stage-based estimate).

    —of the demand in your selection you can still deliver to

    Where several sectors buy the same kit

    Regions where two or more sectors will tender your category: one framework agreement, several buyers.

    The largest projects in your selection

    Anonymised. Gates on record: P permit · G grid · O offtake · E EPC.

    SectorWhereSizeStageYour categoryGates
    See every named project, its developer and the tender date

    Vendor Intelligence names the projects behind these numbers, alerts you before each tender opens, and ranks them by bankability so your bid team works on the ones that will be built.

    Modeled, not filed: demand is each project's capex times the typical share of that equipment in its sector's bill of quantities. Lead times and supply risk from Setcoin's vendor screen. Figures update as the Atlas does.

    01 · The lead-time wall

    Demand by category, coloured by supply risk

    Bar length is modeled demand; the label is the delivery lead time from an order placed today.

    Turbines & modules12,337 projects · 1 sector$809.9bn12–24 mo · Normal
    BESS containers12,337 projects · 1 sector$289.2bn12–18 mo · Normal
    Power transformers14,853 projects · 4 sectors$288.4bn48–66 mo · Critical
    Liquid cooling & CDU127 projects · 1 sector$232.6bn18–30 mo · Tight
    Balance of plant12,337 projects · 1 sector$231.4bn12–18 mo · Normal
    Inverters & converters12,337 projects · 1 sector$154.3bn12–18 mo · Normal
    Cable & overhead line2,389 projects · 2 sectors$142.4bn30–48 mo · Critical
    UPS & standby generation127 projects · 1 sector$139.5bn24–36 mo · Tight
    Structural & envelope321 projects · 3 sectors$129.7bn12–18 mo · Normal
    MV switchgear127 projects · 1 sector$93.0bn30–42 mo · Critical
    White space & busway127 projects · 1 sector$81.4bn12–18 mo · Normal
    MV/HV switchgear2,389 projects · 2 sectors$73.1bn30–42 mo · Critical

    Critical — order now or miss the windowTightNormal

    02 · Where the demand sits

    Region × category heatmap

    Darker cells hold more modeled demand. Hover a cell for the value and project count.

    Turbines & modulesBESS containersPower transformersLiquid cooling & CDUBalance of plantInverters & convertersCable & overhead lineUPS & standby generationUnited States$85.2bn$82.5bn$162.4bn$97.5bnEurope & UK$577.9bn$206.4bn$161.7bn$165.1bn$110.1bn$102.4bnCanada$61.5bn$36.9bnAsia-Pacific$82.6bnLatin AmericaMiddle East & Africa

    03 · Joint tender pools

    Same kit, same region, different sectors

    Projects that never meet in one queue still buy the same transformers, switchgear and cable. Grouped, they can tender together — better slots, better prices.

    Europe & UK

    Power transformers

    $161.7bn

    10,799 projects across 4 sectors: Power & renewables, Grid, Transmission, Data centres

    Europe & UK

    Cable & overhead line

    $102.4bn

    311 projects across 2 sectors: Grid, Transmission

    United States

    Structural & envelope

    $96.7bn

    112 projects across 3 sectors: Data centres, Semiconductors, Manufacturing

    United States

    Power transformers

    $82.5bn

    2,264 projects across 4 sectors: Power & renewables, Grid, Data centres, Transmission

    Europe & UK

    MV/HV switchgear

    $49.0bn

    311 projects across 2 sectors: Grid, Transmission

    United States

    Cable & overhead line

    $33.3bn

    1,852 projects across 2 sectors: Grid, Transmission

    How the Crosslink engine finds these pools →

    04 · The supply side

    What suppliers can deliver

    31 suppliers screened on capacity, backlog and slot availability, and matched to the pipeline above.

    Production-slot risk

    Low6
    Medium5
    High3

    Share of screened suppliers by how hard it is to secure a production slot today.

    Capacity coming online

    • Caterpillar (incl. Solar Turbines)Large-engine capacity ~3× 2024; Solar Turbines 2.5×; Wamego repurposed for Solar packagingUS · 2026–2029 · under way
    • EatonBellevue (Omaha) NE switchgear plant — 370k sq ft, AIS and GIS, 200+ jobsUS · 2027 H1 · announced
    • Siemens EnergyUS $1bn: Charlotte LPT factory + GT restart, Winston-Salem components, Raleigh grid engineering (1,500 jobs)US · 2027–2028 · construction started
    • Schneider ElectricMt. Juliet TN MV switchgear campus (building 2 under construction)US · 2026–2027 · part operating
    • Schneider Electric$700m US manufacturing investment through 2027US · 2025–2027 · under way
    • Applied MaterialsChandler AZ critical-component manufacturing facilityUS · 2027 · announced

    Open the vendor screen →

    05 · Who uses it

    One map, three decisions

    OEMs & suppliers

    See demand 12–36 months before the RFQ, by category and region, and plan capacity and sales coverage against it.

    Setcoin for Vendors →

    EPCs & developers

    Lock long-lead items early, join a tender pool, and show lenders a procurement plan that survives the lead-time wall.

    Setcoin for Developers →

    Lenders & investors

    Test schedule risk in diligence: which projects depend on critical-lead equipment that is not yet ordered.

    Setcoin for Capital →

    Demand is modeled: filed capex where a record carries one, otherwise capacity × a sector rate, split by fixed sector shares per equipment category. Lead times are market ranges, not supplier quotes.

    Equipment Map

    About the Equipment Map

    What is the Setcoin Equipment Map?

    A view of what the world's infrastructure pipeline will buy: modelled equipment demand across 15,423 pre-FID projects, by category, region and lead time, with the supply risk for each category and the vendors that can deliver.

    How is demand modelled?

    Each sector's capex splits into known equipment shares. Those shares are applied to every pre-FID project with a filed or modelled capex, then summed by category and region. It is a model of demand, not a list of orders.

    What is a joint tender pool?

    A group of projects in the same region that need the same equipment around the same time, often across different sectors. Buying together can secure manufacturing slots and better terms when lead times are long.

    Which equipment is hardest to get?

    Categories flagged Critical have the longest lead times relative to demand — Power transformers, Cable & overhead line, MV switchgear, MV/HV switchgear. Projects that need them should reserve slots before FID.