Procurement, EPC & Supply Chain Analysis

What does a datacenter cost per MW to build, and which equipment sets the schedule?

Chapter summary

Equipment lead times, not construction, now set the critical path. The chapter benchmarks delivery models, MEP costs per MW and regional construction costs, and shows how transformer and switchgear lead times have stretched since 2023.

Key takeaways

  1. 1

    Transformer lead times rose from 32–40 weeks to 52–78 weeks between 2023 and 2025.

  2. 2

    Total MEP equipment runs $2.9–4.4M per MW; power infrastructure alone is $1.4–2.1M.

  3. 3

    Soft costs add 15–25% to hard costs.

Data centres access

Keep reading with Data centres access

This chapter (4 exhibits, 3,637 words) is part of Data centres & digital infrastructure. Data centres access opens every chapter of this report, with the interactive models, Excel downloads, Ask and named Atlas records.

€199 a month or €1,490 a year per sector, after a 7-day free trial. Cancel any time. Need several sectors? All sectors: €999 a month.

Ask about this chapter

Answers drawn from every Setcoin report and the live Atlas. Each statement links to the passage behind it.

Summarise "Procurement, EPC & Supply Chain Analysis" in five pointsWhich figures in this chapter matter most to an investment committee?What should I check on the Atlas after reading this?
Subscription

Ask is included with every subscription

Cited answers across every report and the Atlas, with follow-up questions and a hand-off to the opportunity finder.

Research for professional investors. Not investment advice, and not an offer of any security or fund interest.