Executive Summary and Reading Guide

At what launch price and hardware cost could electricity beamed from orbit compete with firm power on Earth, and what should decision-makers take from the evidence in 2026?

Chapter summary

not soon, and only if two costs fall by large factors at once.

Key takeaways

  1. 1

    Space-based solar power (SBSP) collects sunlight in orbit, where it shines almost all the time, and sends the energy to the ground as microwaves or light.

  2. 2

    NASA's 2024 assessment put the cost of electricity from two reference designs at about $0.61 and $1.59 per kilowatt-hour, ten to thirty times terrestrial renewables, with launch the largest cost.

  3. 3

    Setcoin's model reaches about $357 per megawatt-hour for a design delivering power at 10 kg per kilowatt, launched at $1,000 per kilogram to low orbit, with $2 per watt of hardware; it falls to about $95 at $200 per kilogram and about $50 if mass and hardware costs halve as well.

At a glance

Exhibit 1.1

Proven physics, unproven economics

~$357/MWh

Setcoin reference cost (10 kg/kW, $1,000/kg, $2/W)

~$95/MWh

same plant at $200/kg launch

~92%

launch share of capital in the reference case

>800 W · 8.6 km

longest ground power-beaming record (DARPA, 2025)

Source: Setcoin model; DARPA; Space-Based Solar Power: Physics, Costs and the Path to Firm Power from Orbit, 2026–2050, Setcoin Research (October 2026)

The chapter · 896 words · 1 exhibits

At what launch price and hardware cost could electricity beamed from orbit compete with firm power on Earth, and what should decision-makers take from the evidence in 2026?

The short answer. not soon, and only if two costs fall by large factors at once. Space-based solar power (SBSP) collects sunlight in orbit, where it shines almost all the time, and sends the energy to the ground as microwaves or light. NASA's 2024 assessment put the cost of electricity from two reference designs at about $0.61 and $1.59 per kilowatt-hour, ten to thirty times terrestrial renewables, with launch the largest cost. Setcoin's model reaches about $357 per megawatt-hour for a design delivering power at 10 kg per kilowatt, launched at $1,000 per kilogram to low orbit, with $2 per watt of hardware; it falls to about $95 at $200 per kilogram and about $50 if mass and hardware costs halve as well. But space hardware today costs hundreds of dollars per watt, a hundred times more than the design assumes. The field has moved from paper to hardware: demonstrations beamed power in orbit (Caltech, 2023), over 8.6 km on the ground (DARPA, 2025) and are now flying (Cowboy Space's Reason-1, October 2026), and Meta has signed for up to 1 GW from Overview Energy from 2030. The first markets are likely to be military bases, remote sites and power for other satellites, not national grids.

Ten findings

#FindingChapter
1Sunlight in high orbit is available about 99% of the time, against roughly 10–25% capacity factors for ground solarChapter 9
2Beaming physics sets the size of the receiver: a 1 km transmitter at 5.8 GHz from geostationary orbit lights a spot about 4.5 km acrossChapter 25
3Only about 18% of the sunlight reaching a microwave system's arrays becomes grid power; about 6% for laser systemsChapter 27, Chapter 29
4Launch dominates cost: about 92% of capital in Setcoin's reference caseChapter 53
5Hardware cost is the hidden second gap: space arrays cost €200–350/W, a design needs about $1–2/WChapter 47
6Published cost estimates span $48 to $1,590 per MWh because assumptions differ by orders of magnitudeChapter 55
7To match new nuclear ($141–251/MWh) at $2/W hardware, launch must fall to roughly $350–650 per kilogram to low orbitChapter 57, Chapter 59
8A 2 GW plant at 10 kg/kW weighs about 20,000 tonnes: some 200 Starship-class launchesChapter 43
9Defence and remote power will pay first; grid power comes lastChapter 69
10Beam safety, spectrum, astronomy and public acceptance are real but manageable constraintsChapter 35, Chapter 77

Key numbers

MeasureValueSource
NASA reference designs, cost of electricity~$610 and ~$1,590 per MWhNASA OTPS, 2024
Launch share of NASA design costs71% and 77%NASA OTPS, 2024
Setcoin reference LCOE (10 kg/kW, $1,000/kg, $2/W)~$357/MWhChapter 53
Same at $200/kg launch~$95/MWhChapter 53
New nuclear, unsubsidised (US)$141–251/MWhLazard, 2025
Longest ground power-beaming record>800 W over 8.6 kmDARPA, 2025
Largest announced offtakeUp to 1 GW (Meta–Overview Energy)Companies, 2026
Mass of a 2 GW plant at 10 kg/kW~20,000 tSetcoin calculation

The five interactive models

ModelQuestion it answers
Cost of electricity (LCOE)What does a megawatt-hour from orbit cost for given mass, launch price, hardware cost and finance? (Chapter 53)
Efficiency chainHow much sunlight survives each step to the grid, for microwave and laser systems? (Chapter 27)
Beam and receiver sizeHow large must the transmitter and receiver be, and how intense is the beam? (Chapter 25)
Launch campaignHow many launches and years would a plant take? (Chapter 43)
Break-even mapWhich combinations of launch price and hardware cost beat a target power price? (Chapter 59)

Each model can be downloaded as a spreadsheet with live formulas.

How the study is organised

PartChaptersContent
I. FoundationsChapter 2 to Chapter 8Definitions, history, why now, sunlight in orbit, method
II. Concepts and programmesChapter 10 to Chapter 23Designs; Europe, UK, US, Japan, China; companies; the Meta deal; demonstrations
III. PhysicsChapter 25 to Chapter 39Beam size, efficiency, lasers, mirrors, receivers, safety, spectrum, weather
IV. Engineering and costChapter 41 to Chapter 51Mass, launch, assembly, hardware cost, orbit choice, operations
V. EconomicsChapter 53 to Chapter 67LCOE, published estimates, firm power, break-even, sensitivities, value, finance, carbon
VI. Markets and regulationChapter 69 to Chapter 80Defence, data centres, islands, power for satellites, rules, law, acceptance
VII. Outlook and toolsChapter 82 to Chapter 98Scenarios, roadmap, gates, case for and against, lessons, checklist, implications, risks, signals, questions, method

Appendices. A, programme and demonstration reference table; B, glossary; C, Setcoin reference data.

Reading paths

ReaderSuggested path
Utility or energy buyerChapters 1, 9, 53, 57, 63, 71, 82
Space companyChapters 10, 25, 41, 43, 47, 59, 94
Government and defenceChapters 12, 15, 19, 69, 77, 78, 84
Capital providerChapters 1, 21, 55, 61, 65, 88, 96
NewcomerChapters 2, 4, 9, 25, 100

How this study relates to the series

This is the eleventh study in Setcoin's space research programme. Study S3 (space-based datacentres) supplies the cost of space solar arrays; Study S5 (launch economics) supplies launch prices; Study S7 (supply chain) covers solar cells and minerals. Facts are as of October 2026; Setcoin calculations and illustrations are labelled.

Check the live record Space Contracts & Tender Radar · Space Claim Check (free)

Ask about this chapter

Answers drawn from every Setcoin report and the live Atlas. Each statement links to the passage behind it.

Summarise "Executive Summary and Reading Guide" in five pointsWhich figures in this chapter matter most to an investment committee?What should I check on the Atlas after reading this?
Subscription

Ask is included with every subscription

Cited answers across every report and the Atlas, with follow-up questions and a hand-off to the opportunity finder.

Research for professional investors. Not investment advice, and not an offer of any security or fund interest.